Friday, May 21, 2010

Walls Are Up

Click on any of the pictures to make them bigger.



Tuesday, May 18, 2010

Monolithic Foundation Pour

We poured the monolithic foundation and Earth Slab today.

Tomorrow morning we'll put in the rest of the floor joists and be decking the floor by the afternoon.


Monday, May 10, 2010

Footing Forms

Footing Forms are going in today. As usual, we are using footing forms that will stay in place and become the foundation drain. We'll be setting the ICF wall forms tomorrow.

Excavation

Excavation has begun. We're setting foundation footing drains and Insulated Concrete Forms this week. More pictures to follow.....

Tuesday, May 4, 2010

Wall Panels and Site Layout

John and Gordy study the site layout.


Exterior Wall before sheathing and exterior insulation.


Exterior wall with sheathing and exterior foam installed.